Between the MDC’s Clean Water Project, DOT’s CTfastrak construction, and other perpetual repairs, now we can add back in the necessary and annoying tradition of ripping it all up and putting it back down.
The City of Hartford has released the milling and paving schedule for Spring 2014:
STREET | LIMITS | MILLING DATE | PAVING DATE |
Hamilton | Brookfield to Pope Park Hwy | 4/25 | 5/5 |
Wethersfield* | Eaton to Airport | To Be Decided | 5/11 – 5/12 |
Wethersfield* | Airport to E. Elliot | TBD | 5/12 – 5/13 |
Flatbush* | Brookfield to Chandler | TBD | 5/14 |
Market* | Morgan St N to Pequot | TBD | 6/2 |
Pleasant St* | Market to N Chapel | TBD | 5/28 – 5/29 |
Sigourney* | Farmington to Collins | TBD | 5/20 |
Sisson Ave* | Park to Capitol | TBD | (info not released) |
Sisson Ave* | Capitol to Gray | TBD | 5/15, 5/18 |
Weston St* | Savitt to Jennings | TBD | 6/3 – 6/4 |
Windsor St* | Trumbull to R.R. Bridge | TBD | 6/1 |
Homestead St* | Albany to Garden | TBD | 5/21, 5/22, 5/27 |
Baltimore St* | Homestead to Albany | TBD | 5/27 |
Pequot* | Market to End | TBD | 6/2 |
Farmington Ave * | Broad to Sigourney | TBD | 5/19 |
Henry St | New Britian to Grandview | Completed | 5/6 |
Grandview Terr | Henry to White | Completed | 5/6 |
Goodwin Park | Hubbard to Maple Ave | TBD | 5/7 – 5/8 |
Dates subject to change due to weather conditions. The asterisks indicate that paving is planned for night time.
Brendan
What do the asterixis mean?
Brendan
Nevermind. I was looking for a corresponding *, not the word asterisks. Nor, did I mean asterixis before.
The above comment is the worst comment I’ve ever left here. I am ashamed.
Kerri Provost
Don’t you have a bar exam to study for or something?
Brendan
Study? That’s not how that test works.